FG: Why We Reduced Mambilla Power Project from 3,500MW to 1,500MW

 

The Minister of Power, Engr. Sale Mamman on Tuesday justified the reduction in the capacity of the Mambilla power project from 3,500 megawatts to 1,500 megawatts, saying it was to ensure adequate funding by lenders.

Minister disclosed this while appearing before the Senate committee on Power said capacity of the power project was rescoped to 1500 megawatts to make it bankable and acceptable to the lenders.

He said: “We discovered that the 3050 megawatts is not visible. We have sent officials to China to review the project and the memo is on the table of Mr President waiting for approval.

“The idea of rescoping the project is to make it bankable. The market that we are operating today in Nigeria is different from the market that was operated when the Mambilla project was conceived.


“Today we need a project that can be paid for in the market. We are funding the project with loan from a lender who is only interested in funding a project that can pay back the loan. Most of the issues around the Mambilla power plant are on bankability of the project. What we did was to redesign the project to be bankable and acceptable to the lenders.”

In his speech, Chairman of the committee, Senator Gabriel Suswam, asked the Minister to account for the N812 million the federal government paid to the Taraba State government for surveying and demarcation of land where the project would be sited.

Suswan said the ministry must account for how the money was used since it given by the federal government adding that “it is left for you to ask the Taraba government to furnish you with the details of how the N812 million was spent”.

A member of the committee, Senator Yusuf A. Yusuf, however, expressed concern that paying the money to the state government would make it impossible for the Senate panel to oversight how the money is spent.

He said: “We can’t appropriate money for land survey and demarcation for Mambilla power project and the money is given to Taraba government to engage land surveyors. This is make it difficult for the Senate to oversight the usage of the money”.

Responding, the Minister said the money was paid to Taraba State government based on the agreement between the state and the federal government.

“We entered into agreement with the state to support it with money to engage firms, based on the local procurement process, to survey and demarcate the land it donated for the project,” he said.

The $5.8 billion Mambilla power plant in Taraba State planned over three decades ago was designed to generate 3,050 megawatts of electricity.

In 2017, the federal government approved the construction of the project to a Chinese state firm.

China’s Export-Import Bank will provide 85 percent of the funding and Nigerian government will supply the remaining 15 percent for the joint venture.


VANGUARD 

Comments

Popular posts from this blog

Taraba State University Joins ASUU Ultimatum to 21 Universities Over 2025 Agreement

The Academic Staff Union of Universities (ASUU), Taraba State University (TSU) chapter, has joined 20 other state-owned universities placed on a 14-day ultimatum over the alleged non-implementation of key provisions of the 2025 Federal Government-ASUU agreement. The ultimatum was issued following resolutions reached at ASUU’s National Executive Council (NEC) meeting held at the University of Abuja, where the union expressed concern over what it described as the “haphazard implementation” of the agreement. ASUU warned that the affected universities could face industrial action if the outstanding issues are not resolved within the 14-day window. The union authorised the affected branches to begin formal processes for strike action should their respective university authorities fail to address the issues. Taraba State University, Jalingo, was specifically listed among the 21 universities affected by the directive. Other institutions on the list include Nasarawa State Universit...

Truck Drivers Block Jalingo–Zing–Yola Road Following Dispute at NDLEA Checkpoint

Taraba Facts Truck drivers have reportedly blocked the Jalingo–Zing–Yola road following a disagreement with a soldier at an NDLEA checkpoint last night. The incident has disrupted movement along the major highway, leaving motorists and other road users stranded. As of Thursday morning, the road remains blocked, with the situation reportedly affecting the free movement of vehicles along the route. The circumstances surrounding the disagreement between the truck drivers and the security personnel remain unclear. Residents and road users are calling on relevant authorities to urgently intervene, investigate the incident and resolve the dispute to restore normal traffic. Authorities are also urged to ensure that the matter is properly addressed and that the safety and movement of commuters along the busy route are not further compromised.

Taraba Begins ₦5,000 Deduction for Teachers’ Permanent Identity Cards

The Taraba State Universal Basic Education Board (TSUBEB) has initiated a ₦5,000 deduction from teachers as part of arrangements for the production of Permanent Identity Cards for teachers across the state. According to UBEC, the identity cards are expected to strengthen staff records, improve security and enhance administrative efficiency in the management of teachers across Taraba State. UBEC further said the Permanent Identity Card project is also expected to assist the state government in developing an accurate and verifiable database of teachers. Such a database will provide Governor Agbu Kefas with reliable information on personnel within the basic education system and support more effective planning, monitoring and personnel management. The initiative is therefore expected to strengthen security measures, improve staff verification and provide a more efficient system for managing personnel across Taraba State’s basic education sector.